Supply, installation and commissioning completed inside a 72-hour window.
A medium-voltage switchgear replacement was executed within a 72-hour planned shutdown, covering supply, removal of legacy panels, installation, cable termination, testing and commissioning.
Pre-shutdown preparation included full factory acceptance testing, staged delivery of panels to site and a rehearsed installation sequence.
The plant restarted on schedule with all protection settings verified and as-built documentation handed over.